Floodplain restoration in the Lonjsko Polje Nature Park in Croatia

Year of issue
2025
Summary

The Lonjsko Polje Nature Park, located along the Sava River, is one of the largest floodplains in Europe and a key retention area in the Croatian section of the Sava basin. Between 2006 and 2008, the restoration project aimed to improve the natural flood retention capacity of the floodplain by enhancing its ability to store excess water and reduce downstream flood risks. The intervention contributed to increasing the water retention volume from 634 million to 733 million cubic meters, using non-structural measures and improved management of embankments and natural flood dynamics. The area also serves as a vital biodiversity hotspot, especially for migratory birds and wetland habitats.

Since the original project, further efforts have continued under the Sava Parks II programme and national conservation strategies. As of 2025, restoration activities include the re-connection of former meanders, targeted flooding of over 200 ha of wetland areas, and the rehabilitation of at least 500 ha of degraded pastures in zones like Krapje Đol and Rakita. Monitoring and long-term management have been reinforced through the implementation of the PEM 103 management plan (2024–2033), including biodiversity tracking, invasive species control, and education programs. Remote sensing and satellite tools are now used to support environmental monitoring in collaboration with OIKON and the European Space Agency.

These ongoing efforts confirm the strategic importance of Lonjsko Polje for nature-based flood management, ecological restoration, and landscape-scale wetland conservation in the Sava River basin.

Photo Gallery
Location
45.3616, 16.8333
Project
NWRM
National ID
Croatia_01
Sector
Hydromorphology
Installation Date
2006
Implementation status
Ongoing
Contact
Adriana Raveau, ACTeon

Overview

Location of the project
The Central Sava Basin (CSB), located in Croatia, is an area that combines natural values with the function of storage of floodwaters of the Sava River. One of the most important areas is the Lonjsko Polje area. About 23 706 ha of this Nature Park, which has an area of approximately 50 600 ha, is used as the largest detention area in the Central Sava Basin.
Country
Croatia
NUTS2 Code
Kontinentalna Hrvatska
Sponge measures implemented in the case study
Floodplain restoration and management
Reconnection of oxbow lakes and similar features
Re-meandering
Involved partners
Authority type Authority name Authority role Comments Authority responsibility
Nature park Lonjsko Polje Nature Park Implementation Nature Park Responsible
Regional / sub-national water authority Croatian Water Agency Financing — Supporting
Documents
Document

Site Information

Climate Zone
Cool temperate moist
Precipitation
872.00 mm
Temperature (°C)
9.50 °C
Runoff
680.00 mm
Elevation range
113
Slope range
gentle (2-5%)
Vegetation class
Natural landscape elements and European riverine lowlands (reed, poplar, willow, ash, willow reed, alder, beech, oak hornbeam...).
WFD Ecological status
Bad
WFD Chemical status
Failing to achieve good
Water quality status
Upstream pollution comes from cities like Zagreb, Kutina, Bjelovar, and Sisak, where sewage plants, a fertilizer dump, an oil refinery, and an herbicide plant contribute to water quality pressures in the Sava basin.

Design and Implementation

Project scale
Large
Project scale specifications
About 23 706 ha (237 km²) of this Nature Park is used as the largest detention area in the Central Sava Basin.
Project area
23706
Project area specifications
Lonjsko Polje represents approximately 184 km² of retention area out of a total basin of 246 km²; 60% in floodplain forests, 30% wet meadows and pastures, the rest agricultural or aquatic areas.
Area subject to Land use change or Management/Practice change (ha)
17100.00 ha
Principles
Integrative planning, integration of demands, acceptable costs, impact on public perception and acceptability, aesthetic benefic, functionality, adaptability.

Financing

Total cost information
The project saves considerable costs, by reducing the amount of water engineering construction: both the length of dikes and the number of distribution facilities are lessened. Accordingly, maintenance costs are also reduced. Additional costs are incurred for designing the new facilities, for modelling the flood waves and for carrying out the risk assessment on the new system.
Incremental costs are needed for important improvements to the system, which will secure the longterm sustainable use of the floodplains. Restoration and rehabilitation projects are needed to achieve an integrated water management.
Costs operation maintenance information
Information not found
Financing authorities
Authority name Type of funding Comments Financing share
European Union EU-funds: LIFE+ LIFE05‑TCY‑CRO‑000111 496 845 € unknown
Croatian Water Agency National funds — unknown
World Bank Other Croatian Inland Waters Project unknown
Compensations
Non

Policy and Governance

Policy description
After severe flooding of the river Sava (Zagreb 1964, Sisak and Karlovac 1965 and 1966) a flood prevention scheme, "Sava 2000" was set up and approved in 1972, with the aim not only to prevent flooding, but also to develop the agriculture. The project was a combination of the construction of large storage areas to retain excess flood water which the Sava cannot discharge, and conventional works (construction of dikes and regulation of the river canal). About 40% of the plan was completed when the region was plunged into conflict in 1990 and Yugoslavia fell apart, leaving large alluvial wetlands unregulated. In the meantime, the vision on ecological values changed. In the year 2000, the World Bank recommended to adjust the 1972 plan to a flood protection scheme that takes into consideration the ecological and landscape diversity values of the floodplains. This 'World Bankplan' proposed measures to mitigate the detrimental impacts on the biodiversity caused by the implementation of the first phase of the 1972 plan. Additional objectives of this new approach were to stimulate the preservation and development of the natural and cultural heritage of the Sava area. The Life project "Central Posavina - Wading toward Integrated Basin Management"; fits in this context in particular by promoting an Integrated Sava Basin Management Plan that meets the requirements of the Water Framework Directive.
Policy targets
Improved Biodiversity
Peak-flow reduction
Policy pressure
Directive Relevant pressure
WFD identified pressure 4.1.1 Physical alteration of channel/bed/riparian area/shore of water body for flood protection
WFD identified pressure 4.2.2 Dams, barriers and locks for flood protection
Other non-EU Croatia’s Nature Protection Act
Other non-EU Ramsar’s Frameworks for managing Wetlands of International Importance
Policy impact
Directive Relevant impact
WFD identified pressure Altered habitats due to morphological changes
Part of a wider plan
Oui
Wider plan
Wider plan type Wider plan focus Name Comments
National Water Croatian Inland Waters Project Funded by a World Bank loan.
Public consultation
Non
Has contractual arrangements
Non

Impacts and Monitoring

Impact Assessment Methodology

Performance impact assessment method
Laboratory

Socio-economic Impacts

Benefits and co-benefits
The project saves considerable costs, by reducing the amount of water engineering construction: both the length of dikes and the number of distribution facilities are lessened. Accordingly maintenance costs are also reduced. Additional costs are incurred for designing the new facilities, for modelling the flood waves and for carrying out the risk assessment on the new system.
Incremental costs are needed for important improvements to the system, which will secure the long term sustainable use of the floodplains. Restoration and rehabilitation projects are needed to achieve an integrated water management.
Value added by the preservation and restoration plan results from the improvement of the nutrient sink capacity, protection of the valuable cultural and natural heritage, and the long-term conservation of large inundation areas for transboundary flood protection. The impact on the alluvial forest cannot been foreseen.

Biophysical impacts: Hydrology

Increased water storage
16.00
Increased water storage unit
% Percent
Information on runoff reduction
Information not found
Information on soil moisture
The storage capacity would be increased from 634 billion m3 to 733 billion m3, a 16 % augmentation.
Information on Restoring hydraulic connection
A very important component of the programme is the improved connectivity of water bodies. 27 oxbow lakes and floodplain areas, which were cut off from the ‘live’ river channel, would be preserved in addition.
Information on reducing flood risks quantity
Long-term conservation of large inundation areas for transboundary flood protection.

Biophysical impacts: Biodiversity

Improved biodiversity
Oui
Information on improved biodiversity
Value added by the preservation and restoration plan results from the improvement of the nutrient sink capacity, protection of the valuable cultural and natural heritage, and the long-term conservation of large inundation areas for transboundary flood protection. The impact on the alluvial forest cannot been foreseen.

Biophysical impacts: Water & Soil Quality

Water quality overall improvements
Neutral impact-no change in WQ status
Soil quality overall improvements
Positive impact-SQ improvement
Information on soil quality overall improvements
Improvement of the nutrient sink capacity.

Biophysical impacts: Others

Ecosystem impact climate regulation
No specific impact

Lessons Learned

Key lessons
The purpose of the Life project "Central Posavina - Wading towards Integrated Basin Management" (2006 -2008) was to develop and improve an integrated river basin management approach in Lonjsko Polje Nature Park and at least on a Central Posavina scale. This has been done by in particular developing consultative processes and appropriate structures which involve the various stakeholders for the conservation, utilisation and management of the water resources by ensuring non-structural flood control methods which take advantage of the natural functions of wetlands to supplement or replace existing flood control infrastructure.
Barriers
Comments
Information not found
Drivers
Driver type Driver role Comments
Balancing different objectives Main driver In the year 2000, the World Bank recommended to adjust the 1972 plan to a flood protection scheme that takes into consideration the ecological and landscape diversity values of the floodplains. This 'World Bankplan' would propose measures to mitigate the detrimental impacts on the biodiversity caused by the implementation of the first phase of the 1972 plan. Additional objectives of this new approach are to stimulate the preservation and development of the natural and cultural heritage of the Sava area
Success factors
Success factor type Success factor role
Successful coordination between authorities Main factor
Transferability
The project has had a high demonstration value for other nature parks in Croatia and can act as a good example for how to develop similar management plans in other regions.