Natural bank stabilization and riparian buffer galleries along the Odelouca River, Portugal
The Odelouca River: Natural bank stabilization and riparian buffer galleries as part of mitigation and compensatory measures and through the use of bio-engineering techniques.
This project carried out in the Odelouca River (sub-catchment of the Arade River Basin, Algarve Region, South of Portugal) entailed the implementation of measures focused on the use of bio-engineering or natural techniques for rehabilitation of riparian buffer zones and river banks (such as river banks resectioning and placement of geotextile; live crib walls and vegetated gabions/rock armour construction and placement; planting of rehabilitated banks with native plant species; construction of artificial islands in the river channel, and clearance of invasive riparian plant species).
Today it remains a relevant and effective implementation. However it needs restoration, but there is apparently no intention to restart the project to the original goals.
The measures implemented focus on the use of bio-engineering or natural techniques for rehabilitation of riparian buffer zones and river banks such as: i) resectioning of river banks and placement of geotextile to prevent erosion, retain soil moisture, prevent (re) growth of weeds and invasive plants and create favourable conditions for planted native plants (reed bed removal / placement of geotextile; 100% coco fibre with 2 polypropylene nets); ii) construction of a crib wall and placement of stone filled gabions to stabilise river banks (vegetated rock armour, live cribwalls (i.e Krainer wall), and vegetated gabions); iii) planting of rehabilitated banks with native plant species, collected from cuttings and seeds in the area and grown on in local nurseries (e.g. Tamarix, Oleander, buckthorn and ash); iv) construction of artificial islands in the river channel; v) clearance of invasive riparian plant species (Arundo donax and Acacia sp).
Overview
| Authority type | Authority name | Authority role | Comments | Authority responsibility |
|---|---|---|---|---|
| Other | Agência Portuguesa do Ambiente | Initiation of the measure | The national authority responsible of environmental issues. It was the programme promoter. | Responsible |
| Architects / Engineers | Águas do Algarve | Monitoring | > Type: Águas do Algarve is a private company > Role: also Monitoring and rehabilitation programme | Responsible |
| Research institute / University | University of Trás-os-Montes e Alto Douro (UTAD) [CITAB and Fluvial Ecology Lab] | Determination of design details of the measure | > Type: UTAD is a research institution > It was in charge of the design of the measure and also is responsible for the monitoring activities. | Supporting |
| Regional / sub-national water authority | RICOVER Project (partners linked with Portugal case studies: Águas do Algarve, SA; Administração da Região Hidrográfica do Algarve) | Monitoring | > Type: Private company and water authority > It was in charge of developing studies and also for the monitoring activities. | Responsible |
| Research institute / University | Instituto Superior de Agronomia (ISA, University of Lisbon) | Determination of design details of the measure | > Type: research institution | Supporting |
| Private property owners | Landowners | Other | Their agreement was needed in order to proceed with the works linked to their lands. | Supporting |
Site Information
Design and Implementation
The character of biological quality elements was assessed in relation to longitudinal changes in habitat quality, including riparian quality.
It was necessary to foresee a modification of the river channel, as downstream the dam the river flow varies (will be most likely reduced). The study area was divided into groups of physically similar units and then the extent of given pressures within each unit was assessed; habitat and riparian integrity and types of impact were quantified in the study area allowing impact specific rehabilitation measures to be drawn up. This was done using the KT method.
The reforestation of riparian areas was done with native plant species, collected from local sites and grown in local nurseries. The design of the measures had to take into account the availability of water, and should mimic when possible the natural distribution of plants.
Besides, socio-economic aspects are relevant, as the alteration of the ecosystem is closely related to the economic activities being developed in the basin; in this specific context, irrigated agriculture.
The constrains were related to the private owners that accepted the project in their farms (fewer than expected); the favourable aspects were the possibility to collected native plants in the area that was later submersed by the reservoir, to use them for plant nurseries and to introduce them combined with the soil engineering techniques to stabilize the river banks.
Financing
20,7 €/m2: Cost of the application of geotextile (coco fibre) plus willow stakes in Spain.
Vegetated rock armour
72,3 €/m2: Live cribwalls (Krainer wall): 5 wood logs [h=2m; x=20cm] plus 30 willow (alive) stakes.
Vegetated gabions
3078 €/ha: Vegetation clearance (this is the average cost of 21 implemented projects in Spain). The range was 428 -7019 €/ha
25203 €/ha: Re-vegetation (this is the average cost of 21 implemented projects in Spain). The range was 1614 - 80249 €/ha
Policy and Governance
- WFD identified pressures: 4.2.3 and 4.2.4 Dams, barriers and locks for drinking water and for irrigation; 4.1.2. Physical alteration of channel/bed/riparian area/ shore of water bodie for agriculture
- The Habitat Directive specific pressures: A09: irrigation; A10: Restructuring agricultural land holding (removal of hedges and copses or scrub (A10.01), stone walls and embankments (A10.02); including (temporary) transition from dry to mesic or wet conditions due to irrigation); Diffuse pollution to surface waters due to agricultural and forestry activities (H01.05) and to household sewage and waste waters (H01.08); I01: invasive non-native species; J02.05.04: Modification of hydrographic functioning, general (reservoirs); J02.06.01: Surface water abstractions for agriculture; J03.01: Reduction or loss of specific habitat features; J03.02: Anthropogenic reduction of habitat connectivity
Mass stabilisation and control of erosion rates
Soil formation and maintenance
In turn, natural bank stabilization also leads to multiple benefits, improving all aspects of GES including improvement/regulation of hydrological regime (regulating river flows, improving the hydrological balance, increasing groundwater recharge and summer low-flow, increasing water exchange between the surface and the subsurface environment, and improving chemical and biological status). The improvement of GES also leads to increasing clean water availability and providing a water provisioning service.
Implemented measures thus contribute to the WFD art. 4, FD art. 7, HD objectives 1 & 2, and BD art. 3.
The Liga para a Protecçao da Naturaleza (LPN) presented a complaint to the EC for the violation of the Natura 2000 protected area with the construction of the Odelouca Dam. A ministerial order in 2005 confirmed the continuation of the works, including the conditions stipulated by the EC for its construction.
| Wider plan type | Wider plan focus | Name | Comments |
|---|---|---|---|
| Local | Water | Compensation measures of dam built in this protected area | This was part of a wider plan that included another emblematic and successful project (with national projection) in the area: the reintroduction of the lynx population extinct in the region for several decades. |
| Activity stage | Activity type | Key issues |
|---|---|---|
| Implementation phase | Attempt to inform the community about the project characteristics | It took place too late, when the machines were already in the field. It failed in attracting the residents into the project. |
| Arrangement type | Name |
|---|---|
| Contractual agreement | Agreements between landowners and project implementators |
Impacts and Monitoring
Monitoring System
Maintenance
Impact Assessment Methodology
Socio-economic Impacts
- Reduction of flood vulnerability due to a better developed riparian forest
- Improvement of water quality
* The economic activity of the region is based on traditional activities, which occupied the riversides of the Odelouca with fruit trees (citrus) annual irrigation crops, vegetables gardens and livestock. Traditionally, landowners use as protection for flood risk ripraps and earth embankment, proving memory on past flood events (causing relevant damages). Despite the initial mistrust in the measures to be implemented, most landowners gave their permission to develop works within their property, which will have direct benefits on flood protection, improved soil composition, water availability, and landscape improvement.
- Flood security and protection (delay on flood peaks)
- Amenities (associated to habitat protection): fish and plants, tourism, recreation, and others
- Sediment retention
- Carbon fixation
- Wildlife habitats and ecological corridors
- Streambanks stabilization
- Providing shade, organic matter, food for streams and their biota
- Filtration of chemicals and other pollutants
Biophysical impacts: Hydrology
Biophysical impacts: Biodiversity
Biophysical impacts: Water & Soil Quality
Biophysical impacts: Others
Lessons Learned
- Forested riparian zones deliver a number of ecosystem functions and services such as storing and fixing carbon; serving as wildlife habitats and ecological corridors; stabilizing riverbanks; providing shade, organic matter, and food for streams and their biota; retaining sediments and filtering chemicals (fertilizers and pesticides). Therefore, further to their effect on water yield, they contribute to a wide range of benefits for society.
- Riparian afforestation is by no means just about planting trees but also about introducing other vegetation types such as scrub, mostly through laterally recovering space for the river. Afforestation is compatible (and there are synergies indeed) with riparian clearing (in this case of invasive species).
- Although there is still no evidence available for the Odelouca sub-catchment, it all suggests that nitrogen levels can be reduced in rivers (by plants or microbial denitrification) through forcing water to circulate through afforested riparian buffers.
- The Odelouca case study is a good example about the characterization and assessment of intermittent Mediterranean river systems for restoration and requalification measures, including bioengineering techniques, closely related to green infrastructures.
- Monitoring is critical. River Habitat Survey (RHS) is a good way of assessing habitat quality including riparian complexity, diversity of hydromorphological features and artificialisation of aquatic habitats (features that may affect facets of the local water cycle).
- Riparian vegetation is central to the physical, chemical, and trophic health of streams. However, riparian restoration is still its formative stage and can be a complex process.
- Further efforts on the ex-post assessment of the impacts of vegetation changes on seasonal water yield and flow regime would be required.
| Driver type | Driver role | Comments |
|---|---|---|
| Legal obligations | Main driver | The project advanced and was financed as a consequence of construction of a dam (for water supply to populations in the Algarve) in a Nature 2000 habitat. EU authorities demanded inherent compensation measures in order to accept the dam. |
| Success factor type | Success factor role | Comments |
|---|---|---|
| Successful coordination between authorities | Main factor | Cooperation between Aguas do Algarve, the promoter company of the Odelouca dam, and the rest of stakeholders enables the implementation of the measures relevant for the restoration of damage sections of the river. |
| Attitude of relevant stakeholders | Main factor | Despite the already mentioned initial resistence, the initiative managed to get most of the needed permissions from landowners in order to start the works. 25 landowners accepted. Out of 32 identified private plots, 22 agreed to participate |
| Existing staff and consultant knowledge | — | The bioengineering techniques were successful and appropriated to mitigate the impact of the frequent floods during the fall period. They were adapted to the characteristics of each river reach and this explain the success. |
- The actual physical conditions of the sections
- Suggestions and demands of landowners in order to accept the intervention - Alteration in the erosion processes, which were verified regarding the fragility of marginal habitats and the expansion of the reed.