Improvement of the navigation conditions on the Danube between Calarasi and Braila, Romania
Summary
The project aims to secure year-round Danube Commission fairway depths of 2.5 m between Călărași and Brăila, including during low flows. Since 2022 it has been reframed as “BALA II,” a combined navigation–environment scheme led by AFDJ Galați that restores and renaturalises the Bala bifurcation area. The solution raises the Bala bottom sill from 0 m to 6.5 m (MNC), re-activates an old bifurcation branch, and foresees complementary works on the Old Danube reach, in order to stabilise low-water hydraulics while limiting ecological impacts. Key permits and approvals have been obtained: water management approval (June 2022) and an environmental agreement from APM Călărași (Sept 2023). In Sept 2024 the Government approved the project’s techno-economic indicators (HG 1079/2024). Procurement for design and works was relaunched in 2025 (estimated value ~743.8 million RON; 96-month duration). As of August 2025, no award notice is publicly available.
Photo gallery
Overview
Meet fairway width guidance: provide a fairway width ~150–180 m on this sector.
Remove low-water bottlenecks at defined “critical points”: execute targeted river-training works initially at CP01 Bala (km 347–343), CP02 Epurașu (km 342.7–341.8), CP10 Caleia/Ostrovu Lupu (km 197–195) to secure the fairway during low flows.
Operational outcome targeted: avoid the seasonal ~110 km bypass via the Bala–Borcea branch (which affected navigation for ~140–160 days/year) by restoring reliable low-water navigation on the Old Danube.
| Authority type | Authority name | Authority role | Comments | Authority responsibility |
|---|---|---|---|---|
| National water authority | Ministry of Transport and Infrastructure | Financing | contracting authority | Responsible |
| Architects / Engineers | INTERCONSTRUCT Ltd. | Implementation | — | Supporting |
| Architects / Engineers | CANAL SERVICELtd. | Implementation | — | Supporting |
| Architects / Engineers | SUPERQUATRO GRUP Ltd | Implementation | — | Supporting |
| Architects / Engineers | GandG Ltd | Implementation | — | Supporting |
| Local water authority | River Administration of the Lower Danube | Implementation | beneficiary | Responsible |
Site Information
Design and Implementation
Financing
Total budget: €49,650,516 (RON 218,611,217, incl. VAT). Funding split: 85% Cohesion Fund / 15% Romanian State. (≈ €42.2 m EU, €7.45 m national).
Environmental monitoring (ROMOMED)
Contract price: €7,197,680; funding: 71.12% ERDF / 28.88% national (≈ €5.12 m EU, €2.08 m national).
Current follow-up project (“BALA II”)
Government-approved total investment: RON 1,020,762,000 (incl. VAT; ~€207.5 m at 1 € = 4.9193 RON). Of this, C+M (construction + installation) is RON 841,369,000 (incl. VAT; ~€171.0 m). Financing source: EU funds via the Transport Program 2021–2027 + Romanian state budget (share not specified in the decision).
Policy and Governance
- the creation of "Oxbow lake" type wetlands zone with positive effects on reducing the risk of flooding by mitigating the effect and ensuring lateral connectivity, improving water storage capacity and diversifying habitats; supporting ecological infrastructure (green and blue);
- as the flow on Old Danube Branch (TEN-T core network) will increase, there will be created the conditions for the ecological flow to be reached (Water Framework Directive) and to restore sturgeon migration on this branch;
- increasing the ecosystems potential of the wetlands in the Natura 2000 Sites - the site of community importance (SCI) – ROSCI0022 and ROSPA0039 Ostroave Danube and increasing the water clarity;
- restoring the natural hydrological regime of the meadow (specific vegetation exists and develops);
- restoring the balance in the sediment regime on the Danube by ensuring a sufficient flow on the Old Danube to entrain and transport sediments from the river bed;
- creating the premises of a speed gradient of the balanced flow regime at the distribution between the arms, the restored one and the Old Danube;
- restoring essential ecosystem services by increasing the area of wetlands by approx. 55.7 ha, which would increase flood, drought and disaster protection, supporting biodiversity and storing (sequestering) more carbon (due to high storage efficiency than any other ecosystem) (35% of wetlands have lost since 1970, at a rate three times higher than that of forests): "the ecosystem services of wetlands are enormous, far exceeding those of terrestrial ecosystems”
- promoting the transport on inland waterways by contributing to the achievement of the objectives of European Green Deal, COM(2019) 640 final with net greenhouse gas emissions target by 2050 and 75% of inland road freight to be transferred to rail and inland waterways;
- reduction of GHG emissions with 62,5 - 55% and increases the area of wetlands that are very important absorbers;
Impacts and Monitoring
Monitoring System
Water & sediments: in-situ physico-chemical field tests, laboratory analyses of water and sediment (including suspended load/turbidity; granulometry).
Biota: phytoplankton, macrophytes, benthic macroinvertebrates, ichthyofauna with a dedicated sturgeon and barbel program (captures/registers, telemetry; tracking migration over the Bala bottom sill), plus avifauna and Natura 2000 site checks.
Maintenance
Socio-economic Impacts
Biophysical impacts: Hydrology
Modelled for BALA II (renaturation + raised sill):
• At low flows (Q=2000–4000 m³/s), Alternative A yields up to +1.05 m water level on the Old Danube and +300 m³/s average flow; depth increase up to ~1.2 m vs. 2011. Effects diminish as discharge rises. Long-term: reduces (but does not stop) Old Danube aggradation.
• Noted sediment effects: scour/deficit at Bala, aggradation in the Old Danube (e.g., Caragheorghe bar) linked to unbalanced liquid/solid splits.
Biophysical impacts: Biodiversity
Biophysical impacts: Others
Lessons Learned
Routine dredging proved insufficient and short-lived on this reach. Studies and operational experience show that persistent morphodynamic imbalance (e.g., several metres’ bed-level difference between Bala and the Old Danube) makes “maintenance-only” approaches ineffective, pointing to the need for structural and morphological solutions.
A step-by-step, evidence-based approach under the Joint Statement greatly improved the project. Works were paused, an extensive monitoring programme (ROMOMED) was put in place, and 2D/3D modelling guided design choices. Early NGO and Commission input shaped requirements and oversight.
“BALA II” shows that navigation and ecology can be combined by renaturing the bifurcation and carefully tuning structures. The concept restores an old branch, raises the Bala sill, and aims to increase water levels on the Old Danube at low flow—while maintaining sturgeon migration conditions.
Stable governance and financing matter. Government approval of techno-economic indicators and EU/national co-funding unlocked the follow-up phase, while procurement and permitting required multiple, sequenced steps.
| Success factor type | Success factor role | Comments |
|---|---|---|
| Financing possibilities | Main factor | — |
| Attitude of decision makers | Main factor | Strong institutional lead (AFDJ) with clear objectives aligned to Danube Commission fairway guidance and TEN-T policy. |
| Conducted assessments (incl. economic) | Main factor | Robust modelling and monitoring (3D/2D models; ROMOMED) to design, check and adapt measures. |
| Attitude of relevant stakeholders | Secondary factor | Joint Statement framework with stakeholder engagement (ICPDR/DC/NGOs) improving environmental safeguards. |
| Other | Main factor | Stepwise redesign toward renaturation (“BALA II”) to balance hydraulics and biodiversity (sturgeons). |