Increasing water retention through afforestation, landscaping and reducing the stream gradient in Xiropotamos River Basin, Greece
Summary
In the Xiropotamos River Basin, near the town of Naoussa in Central Macedonia, Greece, a set of natural water retention measures was implemented to address severe erosion, flash flooding, and reduced water availability. The area, affected by deforestation and land degradation, required restoration to stabilize soils and improve hydrological regulation.
The project, initiated in 2004 and approved under national environmental terms in 2013, combined afforestation, riverbed reshaping, and small-scale retention structures. Around 70 hectares of degraded land were reforested with native tree species to reduce runoff and increase infiltration. In parallel, a 2 km stretch of the river was reprofiled to reduce its slope, and a series of check-dams and retention basins were constructed to slow water flow and trap sediments.
Implementation was led by the Municipality of Naoussa with the support of a private contractor, and the public development agency AN.KO A.E. contributed to forest technical works in the mountainous upstream areas. The intervention stands out as one of the first in Greece to combine forest hydrological engineering with landscape restoration at basin scale.
The project helped decrease peak flows, reduce sediment transport, and improve local water retention. It also provided environmental co-benefits by restoring vegetation cover and stabilizing the catchment. Its approval under Greek environmental regulations highlights its formal recognition and alignment with national water and forest policy objectives.
Photo gallery
Overview
Increase water retention and infiltration via restoration and vegetation.
Mitigate soil loss and improve hydrological regulation at sub‑basin scale.
| Authority type | Authority name | Authority role |
|---|---|---|
| Regional / sub-national water authority | The Decentralised Administration of Epirus and Western Macedonia, Directorates General of Land Planning and Environmental Policy, Directorate of Environment, Land Planning of Western Macedonia, Department of Environment and Land Planning | Determination of design details of the measure |
Site Information
Design and Implementation
Financing
Policy and Governance
Impacts and Monitoring
Impact Assessment Methodology
Socio-economic Impacts
Biophysical impacts: Hydrology
Biophysical impacts: Biodiversity
Biophysical impacts: Water & Soil Quality
Biophysical impacts: Others
Lessons Learned
One of the key lessons is the importance of integrating forest and hydrological engineering in a basin-scale approach. The coordinated use of reforestation and check-dams allowed for both slope stabilization and a reduction in peak flows. This approach may be replicable in similar environments where erosion control and water retention are priorities.
The project also shows the value of institutional collaboration. It involved local authorities (Municipality of Naoussa), a public development agency (AN.KO A.E.), and national oversight through environmental approval by the decentralised administration. This structure helped align the intervention with regional and national environmental policy.
However, a major limitation is the lack of long-term monitoring data. Without quantifiable evidence of hydrological, ecological, or socio-economic impacts, it is difficult to fully assess the project’s effectiveness or guide adaptive management. This highlights the need for structured follow-up and impact assessment in similar projects.
Finally, the case underscores the potential of pilot-scale, EU-funded initiatives to test nature-based solutions in real-world settings. Yet, it also suggests that such efforts must be accompanied by transparent documentation and accessible evaluation data to inform broader policy and practice.
| Driver type | Driver role | Comments |
|---|---|---|
| Other | Main driver | The improved mountainous hydrology of the area. |
| Success factor type | Success factor role | Comments |
|---|---|---|
| Attitude of decision makers | Main factor | The decision makers approved the relevant environmental impact assessment |