Résumé
This case study focuses on the restoration of the Aurino stream as part of a 20-year management plan (1999–2020), during which several interventions were implemented between Molini di Tures and Brunico. The main goal was flood protection, alongside ecological restoration.
Since 2003, several restoration and requalification interventions have been carried out on areas of public water property. The measures included widening the riverbed, reactivating side channels, lowering embankments, and restoring sediment dynamics. Specific interventions carried out under these objectives included: the widening of the Aurino river section at Molini II; requalification of the Aurino at Molini; requalification of the Stockweiher; requalification of the Gatzaue area; requalification of the Schmidt-Aue floodplain; and requalification of the lower course of the Rio di Fontecervo. Additional efforts included the creation of the San Giorgio River Park “Beach”; widening of the “Im Sack” meander; and widening of the “Raut” area, including the oxbow lake. Complementary awareness and recreational initiatives such as Views on the Aurino, the Experience the Aurino trail (Lower Aurino river recreation), and the river recreation area in Eile further supported the engagement and multifunctional use of the restored areas. Most works were conducted on public land; however, one intervention (Gatzauer/Gais Lot III) required compensation due to the use of private property.
Stakeholder involvement from farmers to local communities was crucial. Negotiations helped balance environmental goals with agricultural needs, leading to broad acceptance. The restored floodplains improved retention capacity (from 17% to 20%), effectively reducing flood risk, as proven during heavy rainfall in 2020 with no reported damages.
The project is still ongoing and there is work being done every year. There is also a monitoring program which is being repeated around every 7 years. Until today the project still proves its effectiveness. Naturally there is some deterioration for example due to the missing sediment input in the catchment. However, to this day there were no restoration works needed for any of the revitalization measures. However, in the near future there will surely be some work done to fight deteriation due to the limited land availability.
Photo gallery
Vue d'ensemble
| Authority type | Authority name | Authority role | Comments | Authority responsibility |
|---|---|---|---|---|
| Regional / sub-national water authority | Autonomous Province of Bozen | Initiation of the measure | Project owner | Responsible |
| Architects / Engineers | Agentur für Bevölkerungsschutz | Implementation | Part of the public administration of the province of Bozen. Their workers do all the planning and even carry out the construction work. | Responsible |
| Other | “Amt für Wildtiermanagement” (office of wildlife management) | Monitoring | fish surveys | Supporting |
| Architects / Engineers | Revital | Monitoring | external ecological planning office for 2018 monitoring | Supporting |
| Other | BeNature | Monitoring | external ecological planning office for 2025 monitoring | Supporting |
| Other | Mountaineering | Monitoring | Hydraulic studies | Supporting |
Site Information
Design and Implementation
1. Agriculture: 300 ha 55%
2. Water body: 50 ha 9%
3. Riparian forest: 70 ha 13%
4. Other (settlements, industrial zones, infrastructure etc.) 23%
The project was divided into 3 phases:
1. Assessment of the current situation
2. Development of vision (catalogue of measures/action plan)
3. Implementation of these measures
The principle behind the project was to take continuous small steps, based on a clear vision, to improve the ecological state of the lower Aurino.
The project profited heavily from the site, as it is one, if not the river with the most public land surrounding it. Also, the ecological condition of the surrounding areas played a key role, as they were in a good state in comparison to other areas in South Tyrol. Furthermore, the river itself wasn’t as morphologically degraded as other rivers in South Tyrol (e.g. no channelization and few bank protection measures such as revetments). Summarizing, the lower Aurino and its surroundings were in a relatively good shape already before the revitalization measures.
Financing
Costs per site:
Campo Tures (all three lots): 345.000 €
Gatzaue/ Gais (all four lots): 917.000 €
Brunico: 1.193.000 €
Coordination and collaboration with universities conducting research/monitoring
Equipment maintenance (piezometers, monitoring instruments)
Data collection and occasional reporting
Actual amounts likely stable or slightly increased but still limited due to funding constraints.
In Gatzaue/ Gais Lot III most of the land (0.6 ha) was privately owned. Once the measures were implemented, the landowner received in exchange other parcels. Some parcels on the old Aurino river bed were in fact still inventorized as "demanio idraulico" (state hydraulic property), but they cannot be considered anymore as part of the hydraulic private property as they are completely covered by woodland. These parcels were given to the private landowner as an exchange, whereas the formerly private parcels used for implementing the measures passed onto the hydraulic public property as they are now occupied by the river.
Policy and Governance
The issue described above are due to (i) hydromorphological interventions on Aurino's effluents, and on 40% of the Aurino stream: this led to the reduction of solid transport; and (ii) intense gravel mining along the lower stream course (in the 70's).
| Wider plan type | Wider plan focus | Name | Comments |
|---|---|---|---|
| Regional | Water | Lower Aurino Management Plan | Management Plan for the Aurino river developed by the Autonomous Province of Bozen |
| Project based | Water | River Basin Agenda | All interventions are part of the Lower Aurino Management Plan, and they are also included in the project "River Basin Agenda" (Alpine Space - Interreg IIIB) aimed at addressing common challenges of alpine river basins. Essential functions and use of river basins are flood protection und flood retention, extensive agriculture and forestry, recreational use, groundwater protection and nature conservation. Modern river basin management therefore means conciliating these requirements at the best possible way. River basin management as it is understood within the project group of the RBA, deals with coordination of procedures regarding flood protection and land use planning in Alpine valley floors. The river basin management plays particularly a crucial role in the spatial development of endangered, intensively used valley sites. In the frame of the planning process it is important to integrate as many participants as possible, e.g. municipalities, departments, interested and concerned people, etc. At the regional level, the interventions aimed at addressing both flood control and the enhancement of riparian environments. |
| Activity stage | Activity type | Key issues | Comments |
|---|---|---|---|
| Design phase | Several activities targeting local communities and stakeholders (e.g. negotiations with farmers, educational activities in schools) | In the Beginning there was a lack of understanding for the vision and the proposed measures. Through public information activities and specific school projects we were able to improve the understanding of the community. The clear and continuous dialogue helped to gain the trust of the stakeholders, specifically the landowners. | informing and involving local communities and key stakeholders was the key to successful implementation (see e.g; negotiations with farmers); |
| Other | Stakeholders yearly meeting | — | Once a year there is a meeting of all stakeholders where problems are being discussed, and new measures are being created. |
| Arrangement type | Name | Comments |
|---|---|---|
| Other | Negotiation with local farmers | Agreement with local farmers: if the groundwater table exceeds the threshold agreed upon, the Province committed to intervene to bring the level below the threshold |
Impacts and Monitoring
Monitoring System
Groundwater levels (most critical)
Channel pattern and planform
Connection to groundwater (hydrogeological parameters)
Riparian shore zone structure and condition
Piezometer levels (regularly)
Invertebrate populations (biological indicators)
Fish and bird populations (ecological status)
Possibly some socio-economic indicators related to agricultural water use, but no formal monitoring plan on socio-economic parameters noted.
Impact Assessment Methodology
Monitoring combined field observations, piezometric measurements, and biodiversity surveys (fish, birds, invertebrates).
Use of before-after comparison of channel morphology and riparian vegetation structure.
Social surveys and visitor engagement used to assess recreational and educational impacts.
Collaboration with universities provided scientific support for impact evaluation.
Some ecological indicators were measured through direct observation and sampling of habitats.
Use of GIS and aerial imagery for mapping channel changes and riparian vegetation.
Biological surveys for fish, birds, amphibians, and benthic invertebrates.
Compensation costs for private land acquisition or use were recorded separately.
No detailed cost-benefit analysis was reported, but financing focused on maintaining flood safety and ecological improvements.
Cost-effectiveness partly assessed by combining ecological benefits with social benefits (recreation, education).
Socio-economic Impacts
Biophysical impacts: Hydrology
• 350,000 m³ for a 30-year return period (Tr30) flood event
• 720,000 m³ for a 100-year return period (Tr100)
• 1,190,000 m³ for a 300-year return period (Tr300)
These volumes represent the natural flood storage in excess of standard retention volumes and play a key role in flood mitigation, especially for downstream settlements such as San Giorgio and Stegona. The 30-year event attenuation reaches approx. 10 m³/s, and for the 300-year event up to 60 m³/s. This natural capacity should be preserved by avoiding further urban development in flood-prone areas and can be enhanced through controlled floodplain management and minor terrain reconfigurations.
Biophysical impacts: Biodiversity
Despite the morphological improvements the animal populations didn’t grow and repopulate the restored habitats as expected.
Biophysical impacts: Water & Soil Quality
Biophysical impacts: Others
Lessons Learned
Combining ecological restoration with recreational improvements (e.g., access to the water, benches, and paths) increases social acceptance.
Flexibility in plans is necessary when addressing stakeholder concerns, such as modifying the original plan at S. Giorgio/Brunico to avoid large forest clearing.
| Driver role | Comments |
|---|---|
| Main driver | The main objective of the interventions is the improvement of riparian natural environments, coupled with protection against floods. More in detail, the interventions were aimed at tackling: (i) almost total disappearance of islands and gravel areas; (ii) dramatic reduction of flooding areas. Another major objective is to raise the groundwater level, which has significantly reduced over time. As a result of the former (i) the river has damaged longitudinal hydraulic works, especially near bridges; (ii) riparian forests are now rarely flooded, and this disturbs ecological dynamics. However, a lower groundwater table allowed the expansion of agricultural areas, and this had to be taken into account when designing and implementing the measures - i.e. bringing back the ground water level back to the original level would not have been a desirable outcome for farmers. The issue described above are due to (i) hydromorphological interventions on Aurino's effluents, and on 40% of the Aurino stream: this led to the reduction of solid transport; and (ii) intense gravel mining along the lower stream course (in the 70's). |
| Success factor type | Success factor role | Comments |
|---|---|---|
| Public participation | Main factor | Participatory planning and communication activities: informing and involving local communities and key stakeholders was the key to successful implementation (see e.g. negotiations with farmers). |
| Communication activities | Main factor | Participatory planning and communication activities: informing and involving local communities and key stakeholders was the key to successful implementation (see e.g. negotiations with farmers). |
| Existing institutional framework | Main factor | The Autonomous Province of Bozen has, as its name suggests, almost full autonomy when it comes to land and river management. This means that it has full responsibility and control over its territory and water bodies, so it can autonomously plan and implement interventions. In addition, it is one of the richest local administrations in Italy, and thus it has funds available. The measures were fully implemented by the Province, which has all the necessary equipment, and nothing was externally contracted or subcontracted: this allowed for keeping the costs down. Interventions were managed by a "strong" coordinator, who had everything under control. |
| Financing possibilities | — | The Autonomous Province of Bozen has, as its name suggests, almost full autonomy when it comes to land and river management. This means that it has full responsibility and control over its territory and water bodies, so it can autonomously plan and implement interventions. In addition, it is one of the richest local administrations in Italy, and thus it has funds available. The measures were fully implemented by the Province, which has all the necessary equipment, and nothing was externally contracted or subcontracted: this allowed for keeping the costs down. Interventions were managed by a "strong" coordinator, who had everything under control. |
| Attitude of decision makers | Main factor | The Autonomous Province of Bozen has, as its name suggests, almost full autonomy when it comes to land and river management. This means that it has full responsibility and control over its territory and water bodies, so it can autonomously plan and implement interventions. In addition, it is one of the richest local administrations in Italy, and thus it has funds available. The measures were fully implemented by the Province, which has all the necessary equipment, and nothing was externally contracted or subcontracted: this allowed for keeping the costs down. Interventions were managed by a "strong" coordinator, who had everything under control. |
Negotiations with farmers influenced design to balance ecological goals and agricultural needs.
The approach demonstrates good transferability due to its focus on participatory planning and balancing ecological with agricultural and recreational needs.
Communication campaigns and involvement of local stakeholders are key transferable aspects.
Therefore, most rivers with a similar concept have not been restaurised to the extend to which the lower Aurion has been renaturalized. The only comparable project is the restauration of the Mareiter Bach/Rio di Mareta, where the first measurements were implemented in 2010 and have since been monitored and worked on