Résumé
Located in Chêne-Bougeries (Geneva canton), this 1995 retention pond demonstrates NWRM in a dense urban plot. The small biotope (~300 m²) stores about 450 m³ on-site and contributes ~279 m³ at the 3.1-ha catchment scale, reducing storm runoff and flood risk. Design details include a lined basin (plastic membrane over sand; clay subsoil), a 1.2-m earth embankment with two overflows (primary outlet limiting discharge to ~48 L/s; emergency crest), and a ~150-m open swale collecting parcel runoff. The pond maintains permanent water (~0.5 m; max depth ~1.6 m); the safety overflow reportedly activated only once, and the basin has not dried out. Works were completed in ~2–3 months (1995) for ≈ CHF 60,000. Maintenance is shared by adjacent owners (annual vegetation removal). Reported benefits include habitat for amphibians, fish and odonates and a reduction in mosquito nuisance. Subsequent ecological survey work in Geneva (2015 sampling; 2018 publication) confirms continued use by amphibians at Étang Vieux-Clos. The approach aligns with the canton’s ongoing strategy to manage stormwater “à ciel ouvert”, with new retention/biotope projects under development nearby.
Photo gallery
Vue d'ensemble
| Authority type | Authority name | Authority role | Comments |
|---|---|---|---|
| Other | Chêne Bougerie town | Initiation of the measure | — |
| — | — | Financing | Architects |
| Private property owners | Solfor SA | Determination of design details of the measure | Architects |
| Private property owners | Jacquet SA | Implementation | Engineers |
Site Information
Design and Implementation
Financing
Policy and Governance
| Wider plan type | Wider plan focus | Name |
|---|---|---|
| National | Water | federal law on water protection, 24 january 1991 |
| Local | Water | Cantonal law on water (L 2 05) |
Impacts and Monitoring
Impact Assessment Methodology
Socio-economic Impacts
Biophysical impacts: Hydrology
Biophysical impacts: Biodiversity
Biophysical impacts: Water & Soil Quality
Biophysical impacts: Others
Lessons Learned
Its success lead to the easy implementation of new water management projects in the city, for example a new retention pond project was presented to the public in 2025.
| Driver type | Driver role | Comments |
|---|---|---|
| Other | Main driver | The main driver which led to consider the measure was the new status of the land which became available to be constructed; water management became a major issue. |
| Other | Main driver | The measure was estimated cheaper than another project (re-build existing infrastructures) |
| Legal obligations | Main driver | The federal law on water protection requests rain water infiltration in urban areas through retention measures |
| Organisation committed to it | Secondary driver | Geneva Canton elaboraed recommandations regarding water retention in urban areas |
| Success factor type | Success factor role | Comments |
|---|---|---|
| Attitude of relevant stakeholders | Main factor | Since private owners are responsible for maintaining vegetation on their plots, the measure efficiency partly depends on their attitude |
| Legal obligations | Secondary factor | Legal obligations can lead stakeholders to implemnt measures to retain water in urban areas |