Horstergrub sediment management, Belgium
Upstream of ’s-Gravenvoeren (Voeren), the Horstergrub measure keeps muddy runoff in the valley with an earthen dyke/dams, and farmland was shifted from maize to grassland to curb erosion. Within the cross-border Aquadra programme (2009–2013), works were delivered: in Dec 2012 an earthen dam and two erosion ponds were built in the Horstergrub to trap water and sediment before it reaches the village. The Horstergrub is a dry valley that only flows during rain; Voeren’s 2023/24 Hemelwater & Drought Plan lists an existing “erosiebuffer op Horstergrub” (~30,600 m²). Since 2022–2024, the Dutch water board notes standard-compliance issues on the Horstergrub in Mheer and is developing a new rainwater buffer near the border at Pletsgatweg (Mesch), in coordination with VMM, with a throttled outlet to limit peaks. Together, these actions complement the original NWRM goal of slowing runoff and reducing sediment delivery to ’s-Gravenvoeren, while addressing today’s cross-border flood-risk needs.
Overview
| Authority type | Authority name | Authority role | Comments |
|---|---|---|---|
| Other | Province of Limburg | Other | The Belgian province of Limburg |
| Other | WRO | Other | The WRO (Waterschap Roer en Overmaas) is the local water authority on the Dutch side of the border. Although not directly involved, RWO Was responsible for a different pilot project upstream on the Horstergrub, also contributing to decreasing the flood risk. |
| Other | — | Initiation of the measure | The local community of Voeren was involved as a full partner, initiating and financing the NWRM and appointing the VMM as executional officer of the program. The community of Voeren was furthermore involved in the entering into compensation agreements with local farmers. |
| Regional / sub-national water authority | VMM | Implementation | VMM was appointed as the executing agent of the project, including the detailed design. |
Site Information
Design and Implementation
The Horstergrub is a dry valley (not a classified watercourse) that conveys intense runoff during rain and points directly toward the village hence repeated water/mud problems.
Financing
Policy and Governance
| Wider plan type | Wider plan focus | Name | Comments |
|---|---|---|---|
| Regional | Water | Aquadra | Aquadra had as a purpose to strive for clean water conditions across regional and national borders. Partners in the project included the Dutch and Belgians provinces of Limburg, province of Liege, regional water authorities from these 3 provinces and the German city of Aachen. |
Impacts and Monitoring
Monitoring System
Impact Assessment Methodology
Biophysical impacts: Hydrology
Biophysical impacts: Biodiversity
Biophysical impacts: Water & Soil Quality
Biophysical impacts: Others
Lessons Learned
| Driver type | Driver role | Comments |
|---|---|---|
| Past flooding events | Main driver | Past flooding events have occurred in the village of Gravenvoeren |